In Delaware, a truck and load can be 8 ft 6 in wide, 13 ft 6 in high and 80,000 lb gross without a permit, with a semitrailer up to 53 ft long on Interstates, federal-aid primary highways and US routes. Anything bigger or heavier needs a hauling permit from the Delaware Department of Transportation (DelDOT), ordered online in its Oversize/Overweight (OSOW) Permit System or through a permit service. DelDOT's Hauling Permit Office answers at (302) 744-2700.
Delaware lets permit loads move seven days a week in daylight, but it keeps oversize through traffic off I-95 in Wilmington. Between the Pennsylvania line and I-495 south of Wilmington, loads up to 120,000 lb must use I-495 instead unless they deliver inside that zone.
Key points:
- Escorts start above 13 ft wide, or at 90 ft long or 15 ft high. Delaware sets no escort driver certification.
- A superload is 15 ft or more wide or high, 120 ft or more long, or over 120,000 lb. DelDOT can take up to 14 business days to review one.
- Holiday bans usually run from noon the day before to 9 a.m. the day after, and Thanksgiving's covers the following Friday too.
- From May 15 to October 1, slow loads can't move from noon Friday to noon Monday on the main beach and through routes.
Delaware legal limits without a permit
These are the most a truck and load can measure and weigh in Delaware without a permit.
| Limit | Legal in Delaware | Where it comes from |
|---|---|---|
| Width | 8 ft 6 in (102 in); on Interstates, federal-aid primary highways and US routes, safety equipment can add up to 3 in on each side | 21 Del. C. §§ 4502(b)(1), 4503(b)(6) |
| Height | 13 ft 6 in, including the load | 21 Del. C. §§ 4502(b)(2), 4503(b)(1) |
| Semitrailer length | 53 ft on Interstates, federal-aid primary highways and US routes | 21 Del. C. § 4503(b)(2) |
| Combination length | 60 ft overall on other roads; 65 ft for car carriers and 70 ft for poles, piling and steel that can't be divided | 21 Del. C. § 4502(b)(3) |
| Single truck length | 40 ft | 21 Del. C. §§ 4502(b)(3), 4503(b)(5) |
| Load overhang | 3 ft past the front; 6 ft past the rear of the bed, or 10 ft for poles, piling, steel and other long items | 21 Del. C. § 4501(g)(2) |
| Gross weight | 80,000 lb for a tractor and semitrailer with 5 or more axles | 21 Del. C. §§ 4501(f)(1), 4503(c)(4) |
| Axle weights | On Interstates, 20,000 lb single and 34,000 lb tandem, within the bridge formula; on other roads, 22,400 lb single and 36,000 lb tandem for a combination | 21 Del. C. §§ 4502(c)(8), 4503(c) |
Off the Interstate, Delaware also allows heavier single-unit trucks: 65,000 lb on three axles and 73,280 lb on four. DelDOT issues single-trip permits that let those grandfathered trucks use the Interstate.
How large a Delaware oversize permit load can be
DelDOT sorts permits by load code. A routine oversize or overweight permit covers loads below superload size, and it's good for five days on the route printed on it. A permit covers state-maintained roads only, with no intermediate stops or round trips.
DelDOT also routes loads around restricted roads:
- Permanent restrictions: these routes are open to loads up to 120,000 lb only when the load delivers inside the restricted area. The best-known is I-95 between the Pennsylvania line and I-495 south of Wilmington. A through move on a restricted route needs individual analysis, typically 2 to 5 working days.
- Temporary restrictions: DelDOT keeps a separate list of road closures, work zones and bridge limits that change often. Check its current Temporary Route Restrictions list in the OSOW Permit System before every move.
- Bridge review: DelDOT's Bridge Management Section reviews any permit with an axle weight of 25,000 lb or more, under the current rules. DelDOT's online FAQ still gives the trigger as an axle over 28,000 lb.
When a Delaware load becomes a superload
DelDOT treats a load as a superload when it's 15 ft or more wide, 15 ft or more high, 120 ft or more long, or over 120,000 lb. The regulation's superload section says 120,000 lb or more instead, so check with the Hauling Permit Office before moving a load of exactly 120,000 lb. Review time depends on the type of superload.
| Superload type | Typical review time |
|---|---|
| Length only | 5 business days |
| Width only | 10 business days |
| Height only | 10 business days |
| Weight only | 10 business days |
| Two or more of the above | 14 business days |
Requests to move outside the normal hours can take up to 14 business days. Expect to provide a route survey (HP Form 16), done within 14 business days before the move, and DelDOT's Superload Gate-Keeping Checklist (HP Form 17). The survey must show at least 6 in of clearance under overhead objects and 3 to 6 in on each side of lateral ones.
Tall loads may need a DelDOT-approved signal contractor, written clearance from utilities and a Delaware certified arborist to trim trees. Loads so wide that traffic can't pass may need police to divert traffic, a traffic control vendor and message boards placed a day ahead. The hauler pays for all of it, and reimburses DelDOT's own costs. Notify the county 911 non-emergency line and DelDOT's Transportation Management Center, (302) 659-4600, at least 1 hour before the move and again when the load arrives or leaves Delaware.
Delaware escort and pilot car requirements
Delaware's escort rules depend on the load's width, length, height, rear overhang and weight. DelDOT lists these defaults in its regulation; the permit's special provisions can add more.
| Load | Escorts required |
|---|---|
| Over 13 ft to 14 ft wide | 1 rear on a multilane highway; 1 front on a two-lane highway |
| Over 14 ft wide | 1 front and 1 rear |
| Over 15 ft wide | 1 front, 1 rear and a Delaware State Police escort |
| 90 ft long or more | 1 rear |
| 100 ft long or more | 1 front and 1 rear |
| 120 ft long or more | 1 front, 1 rear and a Delaware State Police escort |
| 15 ft high or more | 1 front and 1 rear |
| 17 ft 6 in high or more | 1 front, 1 rear and a Delaware State Police escort |
| Over 120,000 lb | 1 front and 1 rear |
| Rear overhang of 15 ft or more | 1 rear, unless the permit says otherwise |
A load that's only overweight, or 12 ft wide or less, can still be assigned escorts if it can't keep up with traffic. Each escort can accompany only one oversize load and must keep visual and two-way radio contact with the driver.
Delaware's rules set no escort driver certification. An escort vehicle must be a single, unpermitted vehicle no smaller than a compact car, with low-beam headlights on. It shows an "OVERSIZE LOAD" sign at least 5 ft long and 12 in high, with 8 in letters, on the roof or on the front and rear. Delaware doesn't require an amber light bar, though escorts may use one.
When Delaware requires a police escort
Delaware's escort table calls for a Delaware State Police (DSP) escort for a load over 15 ft wide, 120 ft long or more, or 17 ft 6 in high or more. DelDOT's superload provisions go further: for a length, width or height superload, the hauler contracts one DSP trooper and patrol car. The two sections don't line up exactly. A load 15 ft to under 17 ft 6 in high, or exactly 15 ft wide, gets a trooper under the superload rules though the escort table doesn't call for one, so check the permit's special provisions. Since November 2022, a load over 120,000 lb no longer needs DSP for weight alone, unless DelDOT adds it.
Notify DSP at least 48 hours before a superload move. DSP escorts are booked through Extra Duty Solutions at (302) 464-6329, and DSP may charge for the service.
When oversize loads can move in Delaware
Delaware permits allow routine oversize and overweight loads to move Monday through Sunday, from sunrise to sunset as set by the National Weather Service.
- Nights: a load up to 75 ft long, 12 ft wide, 14 ft 6 in high and 120,000 lb can move from 9 p.m. to 5 a.m., Monday through Friday, with prior approval. Check the After Hour Move box and request night movement in the application comments.
- Superloads: width, height and combined superloads should avoid 6 to 9 a.m. and 3 to 7 p.m. A weight-only superload should avoid those hours on weekdays if it can't stay within 10 mph of the speed limit.
- Summer weekends: from May 15 through October 1, a load that can't stay within 10 mph of the posted speed can't move from noon Friday to noon Monday. The rule covers I-95, I-295, I-495, US 13 and SR 1 in New Castle County, and US 9, US 13, US 113, SR 1, SR 18, SR 24, SR 26, SR 54 and SR 404 in Kent and Sussex counties.
- Beach areas: during the same season, DelDOT recommends that combined superloads use beach-area routes only Tuesday through Thursday, outside the rush hours.
- Weather: no travel when weather, visibility or road conditions make it hazardous.
Delaware holiday restrictions
Delaware bars permit loads on New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, the day after Thanksgiving and Christmas. DelDOT publishes the exact windows each year, and in 2026 most run from noon the day before the holiday to 9 a.m. the day after.
- Thanksgiving: no moves from noon on Wednesday, November 25, until 9 a.m. on Saturday, November 28, 2026. The Hauling Permit Office is closed November 26 and 27.
- Christmas: no moves from noon on Thursday, December 24, until 9 a.m. on Saturday, December 26, 2026.
- New Year's Day: no moves from noon on Thursday, December 31, 2026, until 9 a.m. on Saturday, January 2, 2027.
Superloads can't move on a restricted holiday or during a special event without DelDOT's permission, requested in writing.
How to get a Delaware oversize permit
DelDOT takes permit applications only online or through an authorized permit service. It doesn't accept them by phone, in person or by fax.
- Register. Create an online account in the DelDOT OSOW Permit System; registration sets up a customer code and a fund account.
- Check your vehicle. Every truck, trailer and self-propelled machine must be registered before you apply.
- Apply. Enter the dimensions, weights, axle data and route. If the load can't travel at the posted speed, say what speed it can hold. Superloads add the route survey, the gate-keeping checklist and a cross-section drawing.
- Pay. Online customers pay from their fund account; DelDOT's user guide explains how to add money to it.
- Carry the permit. Keep it and its supporting documents in the truck. A breakdown can extend the expiration date by 3 days, and bad weather can push it to the next business day the roads are clear; call the Hauling Permit Office before the permit expires.
Delaware oversize permit fees
Delaware charges a flat permit fee plus a weight fee for overweight loads.
| Permit | Fee |
|---|---|
| Oversize single-trip permit | $30 |
| Overweight single-trip permit | $30, plus $10 for each 8,000 lb or part of 8,000 lb over legal weight |
| Superload single-trip permit | $60, plus the same weight fee and any DelDOT support costs |
| Single-trip Interstate permit for a grandfathered three- or four-axle truck | $1 |
| Amending a purchased permit | $10 |
For example, a 100,000 lb load on five axles is 20,000 lb over the 80,000 lb limit, so it pays $30 plus $30 in weight fees.
Planning an oversize move through Delaware
Delaware's 13 ft 6 in height and 8 ft 6 in width match Maryland, Pennsylvania and New Jersey. Length is where the states differ off the main roads: Delaware caps the whole rig at 60 ft there, while Maryland's limit is a 48 ft semitrailer off its Interstates and truck routes. On the main highways, Delaware and Maryland both allow a 53 ft semitrailer. See legal limits in all 50 states, or the Maryland, Pennsylvania and New Jersey oversize guides.
Superload review time drives most Delaware lead times: plan on 5 to 14 business days, plus a route survey that must be fresh within 14 business days of the move. Through loads on I-95 should plan on I-495 around Wilmington from the start. Summer moves toward the beaches lose Friday afternoons through Monday mornings if they can't keep near the speed limit.
Moving a load into, out of or across Delaware? Request a heavy haul quote with the dimensions, weight and route, or see our over dimensional freight service.