Maine oversize rules: legal limits (8 ft 6 in wide, 14 ft high with load), escort triggers, holiday and weekend limits, and how to get a BMV permit.

Updated 5 min read

Legal width
8 ft 6 in
Legal height
13 ft 6 in
The load may extend 6 in higher, to 14 ft; 13 ft 6 in with load on the Maine Turnpike
Semitrailer length
53 ft
Trailers over 48 ft must meet kingpin and axle-spacing limits
Gross weight
80,000 lb; 100,000 lb on 6 axles
First escort
Over 12 ft wide or 80 ft long
Police escort
16 ft wide or 125 ft long
Engineering review
Over 130,000 lb on 5 axles
Holiday rule
No moves on holiday weekends

Permits issued by

Maine Bureau of Motor Vehicles, Motor Carrier Services, Overlimit Permit Unit

Apply online
MoveME
Office hours
Office 8:30 a.m.–4:30 p.m., Mon–Fri
On this page

In Maine, a truck and load can be 8 ft 6 in wide and 80,000 lb gross on five axles, or 100,000 lb on six, without a permit. The vehicle can be 13 ft 6 in high with the load up to 6 in higher, and a semitrailer can be 53 ft long. Anything bigger needs an overlimit permit from the Maine Bureau of Motor Vehicles (BMV), which you order online in MoveME or by phone at (207) 624-9000 ext. 52134.

Three agencies shape a Maine move. The BMV issues the permit on the advice of the Maine Department of Transportation (MaineDOT), which reviews heavy loads and can close roads to heavy vehicles from November 15 to June 1. The Maine Turnpike Authority (MTA) runs the Turnpike from Kittery to Augusta under its own rules. A BMV permit doesn't cover the Turnpike, so you also buy a Turnpike permit at the toll plaza.

Key points:

  • One pilot car starts over 12 ft wide or 80 ft long. A police escort is required by law at 16 ft wide or 125 ft long.
  • Oversize loads move in daylight and can't move on the BMV's 13 listed holidays or its holiday weekends. Summer Saturdays end at 9 a.m. on I-95.
  • A five-axle tractor-semitrailer can be permitted to 130,000 lb before MaineDOT's detailed review. For heavier "extreme loads," allow at least 2 to 5 business days for engineering review.
  • Single-trip permit fees run from $6 to $27.50.

These are the most a truck and load can measure and weigh on Maine highways without an overlimit permit.

LimitLegal in MaineWhere it comes from
Width8 ft 6 in (102 in)29-A M.R.S. § 2380(3)
Height13 ft 6 in for the vehicle; the load can extend 6 in higher, for 14 ft with load. On the Maine Turnpike, 13 ft 6 in with load.29-A M.R.S. § 2380(2); 29-250 CMR ch. 157 § 12; MTA Rule 7(L)
Semitrailer length53 ft, if the kingpin is no more than 45 ft 6 in from the center of the rear axle and other conditions are met29-A M.R.S. § 2390(1)(J)
Overall length65 ft for most combinations. With a 48 ft trailer, no overall limit on the Interstate and designated highways (69 ft elsewhere). With a 53 ft semitrailer, 74 ft off the National Network.29-A M.R.S. § 2390(1)(B), (C), (E), (J)
Single truck length45 ft29-A M.R.S. § 2390(1)(A)
Load overhangCounts toward overall length. A load more than 4 ft past the rear needs a red light at night and a 12 by 12 in fluorescent flag by day.29-A M.R.S. §§ 2390, 2385
Gross weight80,000 lb on a combination with five or more axles; 100,000 lb on a three-axle tractor with a tri-axle semitrailer, including on the Interstate29-A M.R.S. §§ 2353, 2354; 17-229 CMR ch. 306; 29-250 CMR ch. 157 § 12
Axle weights22,400 lb single, 38,000 lb tandem, 48,000 lb tri-axle; 41,000 lb tandem and 50,000 lb tri-axle on a 100,000 lb six-axle combination29-A M.R.S. §§ 2353(4), 2354

A 14 ft legal height with load doesn't mean every route clears it. Maine posts bridge and overpass clearances only when they're under 14 ft 6 in. The BMV's rule notes that many Maine Turnpike bridges are 13 ft 6 in.

How large a Maine oversize permit load can be

Maine's rule sets no fixed maximum width or length for a single-trip permit. Instead, the requirements grow with the load: more escorts, more notice and, past set weights, an engineering review.

  • Weight: the BMV can permit these gross weights without a special and detailed MaineDOT review: 120,000 lb on a four-axle tractor-semitrailer, 130,000 lb on five axles, 140,000 lb on six, 159,000 to 167,000 lb on seven and 177,000 lb on eight. Any axle or axle group gets an extra 3% tolerance.
  • Very wide or long loads: at 20 ft wide or 150 ft long, notify utilities and towns, and move only in clear visibility, outside commuter and school bus hours. At 150 ft or longer, you also handle public outreach, such as a press release and notice to towns.
  • Height: over 15 ft needs a pole car. You're responsible for contacting utility companies about any overhead wires that must be moved.
  • Posted roads: the BMV doesn't grant overweight permits for posted roads, and every permit is subject to all bridge and road postings.

When a Maine load becomes an extreme load

Maine calls a load heavier than the weights above an "extreme load," and it may need detailed engineering reviews by MaineDOT or the MTA. The rule tells you to allow at least two to five business days for that review, and the BMV may ask for an axle weight and spacing diagram. MoveME's login page carries the same warning: extreme-load permits can take a minimum of 2 to 5 business days.

Maine escort and pilot car requirements

The number of escorts depends on the load's width, length, rear overhang and height. These thresholds come from Table 1 of the BMV's permit rule for a Maine-only permit; manufactured and modular homes follow a separate table.

LoadEscorts required
Over 12 ft to under 16 ft wide1 pilot vehicle
16 ft to under 20 ft wide1 pilot vehicle and 1 police escort, or 2 police escorts when the State Police, MaineDOT or BMV requires
20 ft wide or more2 police escorts and 1 pilot vehicle
Over 80 ft to under 125 ft long1 pilot vehicle
125 ft to under 150 ft long1 pilot vehicle and 1 police escort, or 2 police escorts when required
150 ft long or more2 police escorts and 1 pilot vehicle
Rear overhang over 5 ft and under 15 ft 1 in2 pilot vehicles
Rear overhang over 15 ft1 police escort and 1 pilot vehicle
Over 15 ft high1 pole car

A single pilot vehicle drives in front on an undivided highway and behind the load on a divided highway. With two, one leads and one follows. The BMV can require pilots for smaller loads, or extra escorts, when it judges a move needs them.

Maine's rule doesn't call for a pilot car certificate. The driver must be at least 18, have held a license for the two years before the move and know the pilot vehicle rules. The pilot vehicle must be a car or light truck with a gross vehicle weight rating under 8,500 lb. It needs roof-mounted amber lights, an "OVERSIZE LOAD" sign at least 5 ft wide and 12 in high, and two-way communication with the load that reaches at least half a mile.

When Maine requires a police escort

Maine law requires a police escort for any vehicle or combination 125 ft or longer or 16 ft or wider. The BMV can require one for smaller loads, and its rule adds rear overhang over 15 ft. Only the Maine State Police can escort on the Interstate. The State Police must provide an escort when a permittee asks, but county sheriffs and town police can refuse.

You book the escort yourself with the right State Police field troop, at least three working days before the move. State Police escorts are billed at actual cost by the Department of Public Safety, with a four-hour minimum charge. Permits that need State Police escorts generally aren't issued for Saturdays.

When oversize loads can move in Maine

Maine limits oversize loads to daylight, and from late April to mid-November its rule also sets the days of travel.

  • Daylight: from 30 minutes before sunrise to 30 minutes after sunset.
  • April 22 to November 18: Monday through Friday in daylight, and Saturdays from 30 minutes before sunrise until noon.
  • June 3 to August 26: Saturday travel ends at 9 a.m. on I-95 and at noon on other roads.
  • Sundays in July and August: a permit needs pre-clearance from MaineDOT's Traffic Engineering Division. The BMV's summary page says moves aren't routinely permitted on weekends in July and August.
  • November 19 to April 21: the rule and the 2026 holiday letter set no weekend hours, so confirm any weekend move with the Overlimit Permit Unit.
  • Night moves: a Maine State Police troop commander can authorize a night move. At least one State Police officer escorts it unless the troop commander waives that.
  • Overweight only: a load that's only overweight and can keep up with traffic can move at any time of day.
  • Weather: no move when visibility is poor or roads are slick with rain, snow, slush or ice. If Interstate speeds are reduced to 45 mph, leave at the first ramp, rest area or weigh station.

MaineDOT gives a blanket exemption for logging, construction and farm equipment on Saturdays and Sundays in July and August in seven counties: Aroostook, Franklin, Oxford, Penobscot, Piscataquis, Somerset and Washington. Those moves must finish by 9 a.m.

Maine holiday restrictions

On every holiday on the BMV's yearly list, the permit office is closed and overlimit loads can't move. Loads also can't move on the holiday weekends the list names. The only exception is an emergency off-hour move authorized under Section 15 of the BMV's rule. The 2026 list covers New Year's Day, Martin Luther King Jr. Day, Presidents' Day, Patriots' Day, Memorial Day, Juneteenth, Independence Day, Labor Day, Indigenous Peoples' Day, Veterans Day, Thanksgiving, the Friday after Thanksgiving and Christmas.

The rest of 2026 has two restricted stretches, both from the BMV's 2026 holiday letter:

HolidayNo overlimit travel
ThanksgivingThursday, November 26, through Sunday, November 29, 2026
ChristmasFriday, December 25, through Sunday, December 27, 2026

The BMV publishes a new list each year, so check the 2027 list before booking a move around New Year's Day.

How to get a Maine oversize permit

Maine permits are ordered online in MoveME, by fax, at a BMV branch office or through a permit service.

  1. Contact the Overlimit Permit Unit first. The BMV issues permits after that first contact. In MoveME, choose "create a new account" on the login page.
  2. Have your details ready. You need the registration plate numbers and, if your company must have one, a USDOT number. For an overweight permit, the truck must already be registered for the most it can legally weigh. The BMV can also ask for proof of liability insurance.
  3. Apply. Order in MoveME, or fax form MV-226 to (207) 622-5332. A faxed permit must be charged to an existing permit account or paid by card. Most permits can't be ordered more than 10 days ahead.
  4. Pay. The BMV takes money orders, bank drafts, credit cards and personal checks subject to collection. Account holders are invoiced monthly.
  5. Carry the permit and add the other permits. The permit must travel with the load in the permittee's legal name. Buy a Turnpike permit at the toll plaza if you'll use the Maine Turnpike, and get local permits for town or city roads.

Maine oversize permit fees

A Maine single-trip permit fee depends on how far the load exceeds the legal limit. When a load exceeds more than one limit, you pay only the highest fee. These fees come from the BMV's fee rule, last replaced in 2010.

FeeWeight over legalLength over legalWidth over 8 ft 6 inHeight over 14 ft
$6.00Up to 5,000 lbUp to 10 ftUp to 2 ftUp to 5 ft
$8.00Over 5,000 to 10,000 lbOver 10 to 15 ftOver 2 to 3 ftOver 5 to 6 ft
$10.00Over 10,000 to 15,000 lbOver 15 to 20 ftOver 3 to 4 ftOver 6 to 7 ft
$12.50Over 15,000 to 20,000 lbOver 20 to 25 ftOver 4 to 5 ftOver 7 to 8 ft
$15.00Over 20,000 to 25,000 lbOver 25 to 30 ftOver 5 to 6 ftOver 8 to 9 ft
$18.00Over 25,000 to 30,000 lbOver 30 to 35 ftOver 6 to 7 ftOver 9 to 10 ft
$21.00Over 30,000 to 35,000 lbOver 35 to 40 ftOver 7 to 8 ftOver 10 to 11 ft
$25.00Over 35,000 to 40,000 lbOver 40 to 45 ftOver 8 to 9 ftOver 11 to 12 ft
$27.50Over 40,000 lbOver 45 ftOver 9 ftOver 12 ft

A permit that covers two or more loaded moves costs a fee for each loaded move. The MTA charges its own $10 permit fee, paid in cash at a staffed over-limit lane, on top of the toll.

Maine long-term permits for repeat moves

If you move the same equipment often, a long-term permit runs month by month for up to 12 months. An over-dimension long-term permit covers up to 11 ft 6 in wide at legal height, and 45 ft long for a single vehicle or 75 ft for a combination, for $25 a month. An overweight long-term permit covers up to 120,000 lb on a tandem- or tridem-drive tractor with a tri-axle semitrailer, for $65 to $150 a month depending on weight and axles. Neither covers town roads, and every bridge posting still applies.

Planning an oversize move through Maine

Maine and New Hampshire share an 8 ft 6 in legal width and a 53 ft semitrailer limit. Height is where they differ. Maine lets the load ride 6 in above its 13 ft 6 in vehicle limit, for 14 ft overall, but New Hampshire's legal height is 13 ft 6 in. A 13 ft 10 in load can run without a height permit on most Maine roads and still need one in New Hampshire. For other states on the route, see legal limits in all 50 states.

The Turnpike deserves its own plan. The MTA says 55% of interstate truck freight enters Maine through Kittery on the Turnpike. There, the height limit stays at 13 ft 6 in with load, and the widest permit is 14 ft 6 in. A load over 10 ft wide can enter or leave only at toll plazas the MTA designates, and Turnpike permits are good for one day.

Lead time in Maine comes from reviews and calendars. Allow at least two to five business days for an extreme load's engineering review, and give the State Police three working days' notice for an escort. MaineDOT can close state roads to heavy vehicles at any time from November 15 to June 1, which can take the shortest route away from an overweight load. Summer Saturdays and holiday weekends shrink the schedule further.

For a load crossing several New England states, Maine's rule describes a single New England Transportation Consortium (NETC) permit. It covers loads up to 14 ft wide, 13 ft 6 in high and 90 ft long, at up to 108,000 lb on five axles or 120,000 lb on six or more. But a note in the same rule says the NETC process is currently suspended, so ask the Overlimit Permit Unit before counting on one permit.

Moving a load into, out of or across Maine? Request a heavy haul quote with the dimensions, weight and route, or see our over dimensional freight service.

Sources

Official sources, each checked on November 20, 2026.

  1. 1.Maine BMV: Overlimit Permits
  2. 2.Maine BMV: 2026 holiday letter: holidays, holiday weekends and seasonal travel hours for overlimit loads
  3. 3.Maine BMV: MoveME permit system (login page notice on extreme loads)
  4. 4.Maine BMV (via Cornell LII): 29-250 CMR Chapter 157: The Administration of Over Dimension and Overweight Permits (amended 2025)
  5. 5.Maine BMV (via Cornell LII): 29-250 CMR Chapter 156: Fee Structure for Over Dimensional and Overweight Loads, with the State Police escort fee
  6. 6.Maine Legislature: 29-A M.R.S. § 2380: Height and width restrictions
  7. 7.Maine Legislature: 29-A M.R.S. § 2390: Maximum length limits
  8. 8.Maine Legislature: 29-A M.R.S. § 2353: Weight limits
  9. 9.Maine Legislature: 29-A M.R.S. § 2354: Six-axle limits
  10. 10.Maine Legislature: 29-A M.R.S. § 2382: Overlimit movement permits, including police escorts
  11. 11.Maine Legislature: 29-A M.R.S. § 2385: Protruding objects and trailers
  12. 12.MaineDOT (via Cornell LII): 17-229 CMR Chapter 306: Truck Size and Weight Limits on Maine's Interstate Highway System
  13. 13.MaineDOT (via Cornell LII): 17-229 CMR Chapter 308: Seasonal Load Restrictions on Certain State and State Aid Highways
  14. 14.Maine Turnpike Authority: Overlimit Permits
  15. 15.Maine Turnpike Authority: Rules Governing the Use of the Maine Turnpike (Chapter 1, Sections 7 and 10)
  16. 16.Maine Turnpike Authority: We Serve Maine (Turnpike from Kittery to Augusta)

Fide Freight is a member of the Specialized Carriers & Rigging Association (SC&RA).

Oversize load in Maine? We'll plan it.

Permits, escorts, route surveys and specialized trailers, planned state by state and priced in one quote.